Siège Social de Rolf C. Hagen

  • End date of the work: 2006
  • Location: Baie-d'Urfé, QC
  • Cost of construction: 8M$
  • Scope: Energy modelling, Commissioning
  • Project description:

    The improved commissioning made it possible to achieve the performance objectives of this quality building made in turnkey mode. Natural light bathes the cafeteria and atrium, and reflective shelves spread it more in work spaces. Radiant floor heating offers the best possible comfort while not contributing to the mixing and re-diffusion of different odors from the premises. In addition, the absence of electric baseboards makes interior design easier. No irrigation of the land is required thanks to the application of xeroparage principles, thus eliminating fertilizers and pesticides.